Western Specialty Contractors Restores Brick Archways Underneath Historic Eads Bridge Crossing Mississippi River

Words: Bronzella Cleveland

The iconic Eads Bridge crossing the Mississippi River between St. Louis, Mo., and East St. Louis, Ill.The iconic Eads Bridge crossing the Mississippi River between St. Louis, Mo., and East St. Louis, Ill., was the first steel structure bridge of its kind in the United States when it was designed by James B. Eads and opened on July 4, 1874. A significant engineering feat for its time, the historic bridge was in desperate need of rehabilitation from decades of use, repairs and environmental exposure.

In May 2012, the Bi-State Development Agency/Metro (BSDA/Metro) launched a monumental Eads Bridge Rehabilitation project, largely funded through $34 million in federal support, which includes $25 million from American Recovery and Reinvestment Act (ARRA) funds. All phases of the project are scheduled to be completed in 2016 and expected to extend the life of the bridge by 50 years. The top deck of the bridge, which supports vehicle and pedestrian travel, is owned by the City of St. Louis. BSDA/Metro owns the superstructure and the lower deck, which is the rail deck that supports the region’s MetroLink light rail system.

The multi-faceted restoration project includes: replacement of support steel dating from the 1880's, refinishing and repainting the bridge's superstructure using a rust-inhibiting coating, upgrading the MetroLink light rail system, and restoring the brick archways under the bridge that support its foundation.

St. Louis Bridge Company, a large bridge company working throughout the Midwest, hired Western Specialty Contractors, formerly named Western Waterproofing Company, as a subcontractor on the project.

Western's scope of work focused on restoring the bridge's brick archway supports on the Missouri side, which are located about 100 yards from the waterfront and allow roadway traffic under the bridge. Western's work included demo of all concrete patching on the brick archways; removal and replacement of all damaged bricks; and tuckpointing of all deteriorated mortar joints.

"We were contracted to remove and replace 1,256 square feet of bricks and tuckpoint 1,256 square feet of mortar joints. We ended up removing 1,824 square feet of bricks and tuck pointing 469 square feet of bricks," said Western Department Manager Rick Kerperien.

One of the challenges that Western's crews faced on the project included installing bricks in the overhead arches, which reach 30 feet high at their centers. Western found an innovative solution to the vertical challenge.

"We overcame that obstacle by cutting wood strips and anchoring them to the arch ceilings which would hold the new bricks securely in place while being installed. Once the bricks cured, we would remove the wood strips and fill in the holes where necessary," Kerperien said.

Western crews also had to bring in water for mixing the mortar and cleaning, and used generators for electricity on the project. Western's phase of the project was completed in four months.

Holding History Together: The Art of Lateral Restraint in Masonry Restoration
January 2026

The first thing you notice about an old masonry building isn’t always its beauty. Sometimes it’s the bow in a wall or the way time and the elements have tugged at the mortar joints. Every century-old structure carries its story in cracks, tilts, bows, and

Stone Savvy: Helping Clients Choose Stone with Intent
January 2026

In today’s design environment, clients are surrounded by inspiration, endless images, samples, and styles that make choosing materials feel exciting and overwhelming all at once. Within that sea of options, stone carries weight. It defines first impressio

MASONRY STRONG Podcast, Episode 36 Recap: Kim Spahn, CEO of the Concrete Masonry Checkoff
January 2026

On this episode of the MASONRY STRONG Podcast, Justin got to sit down for a conversation with Kim Spahn to talk about the Concrete Masonry Checkoff, how Kim first got involved in this industry, and much more.

From Day One to Long-Term Success: Onboarding Strategies for Contractors
January 2026

The construction industry is facing one of its toughest challenges in decades. Companies are struggling to find enough skilled workers while competing to keep the ones they have. At the same time, projects are becoming more complex, deadlines are tighter,