MayJun 2008: Minimizing Masonry Litigation – Part 3 - Foundations

Words: Bronzella Cleveland


Norm Cooper, P.E.
Norm Cooper, P.E., has served the justice system as a forensic engineer in more than 700 cases. He is included in Who’s Who in American Law and national and international editions of Who’s Who in Engineering. Cooper’s web address is www.realtyengineering.
com
.
Next Edition
Upcoming articles will include case studies of disputes and lawsuits involving other masonry issues.
Norm Cooper, P.E.
Norm Cooper, P.E., has served the justice system as a forensic engineer in more than 700 cases. He is included in Who’s Who in American Law and national and international editions of Who’s Who in Engineering. Cooper’s web address is www.realtyengineering.
com
.
Next Edition
Upcoming articles will include case studies of disputes and lawsuits involving other masonry issues.
Norm Cooper, P.E.
Norm Cooper, P.E., has served the justice system as a forensic engineer in more than 700 cases. He is included in Who’s Who in American Law and national and international editions of Who’s Who in Engineering. Cooper’s web address is www.realtyengineering.
com
.
Next Edition
Upcoming articles will include case studies of disputes and lawsuits involving other masonry issues.

Previous articles in this series covered general principles and drainage. The first article states that lawsuits can be minimized by good ethics, well-written contracts, clear communication, and by following directions (e.g., building codes). The second article illustrates how to avoid inadequate drainage, which moves the foundation and is the most common cause of masonry distress and lawsuits. This article addresses the foundation itself, which is the second most common cause of masonry distress and lawsuits.

Code Principles

To minimize movement, the foundation is required (IBC* 1604, IRC*R401.2) to be designed and constructed (of masonry or other materials) to carry the loads from the building (or other structure) to the supporting earth. Loads from the structure include (IBC*1603, IRC*R301.1) dead loads from the structure itself, live loads from use and occupancy of the structure, and environmental loads such as wind, rain, snow, water action, flood and earthquake. The loads carried through said foundation to the earth are required (IBC*1804, IRC*R401.4.1) not to exceed the capability of the earth to support said loads. Failure to comply with these code principles is a major cause of foundation movement and resulting masonry distress.

Avoiding masonry lawsuits foundations
Photo 1

Case Studies


The following examples (from the author’s expert witness cases) illustrate inadequate masonry foundation design/construction, and illustrate inadequate non-masonry foundations causing masonry distress.

Case #1: Masonry Pier/Beam Foundation. A large percentage of small buildings nationwide (existing and proposed) have a concrete masonry unit (CMU) pier and beam foundation, which can be a practical and economical choice. Unfortunately, many of these foundations do not comply with building codes (and do not comply with loan requirements of the Federal Housing Administration and Veteran’s Administration). These code violations cause economic loss, injury and death (particularly with wind or flood loads), and subsequent lawsuits. One such case, a manufactured home (Photo 1), did not comply with:

a. Required foundation depth below ground (IRC*R403.1.4),
b. Securing of piers from footing up through CMU to house framing (IRC*R401.2),
c. Drainage slopes away from building (IRC*R401.3, R403.1.7.3).

These masonry foundation problems caused moving and cracking of the walls and roof, water entry into home, organisms (mold), and risked injury and/or death. The solution was vertical steel into new concrete footings and up through the hollow CMU, secured to the beams, and then the hollows filled with concrete grout. These costly problems and this costly litigation could have been avoided by complying with the building code.

Avoiding masonry lawsuits foundations
Photo 2

Case #2: Post Tensioned Foundation. Cracks continued to worsen in masonry siding, in slab, and in drywall in a building on a post tensioned foundation on expansive clay (Photo 2). These cracks were caused by violations of foundation construction plan requirements (“a” through “f” below) and by violations of foundation building code requirements (“g” through “I” below):

a. No removal of bad soil.
b. No proof rolling sub-grade.
c. No select fill.
d. No compaction or compaction testing.
e. No thickened slab in high-stress areas.
f. Missing steel reinforcement.
g. Inadequate concrete consolidation (IBC*1905.10).
h. Inadequate slab elevation above public drainage (IBC*1805.3.4).
i. Inadequate drainage around building (IBC*1803.3).

The estimated cost to repair exceeded the estimated cost to remove and replace the building. These costly foundation problems (that showed up first as masonry cracks) and this costly litigation would have been avoided if the building contractor had followed the requirements and/or if inspections were performed by competent personnel (e.g., a licensed professional engineer).

Avoiding masonry lawsuits foundations
Photo 3
Photo 3

Case #3: Slab/Gradebeam Foundation. Extensive cracks in masonry siding (Photo 3) and interior drywall cracks, stuck doors, and excessive slab elevation changes were caused by violation of foundation code requirements in a reinforced concrete slab/gradebeam foundation. These code violations included:

a. Load exceeding soil bearing capacity (IRC*R401.4.1),
b. Shallow gradebeams (IRC*R403.1.1),
c. Slab out of level (ACI*4.4.1) and excessive slab slopes (ACI*4.8.2),
d. Inadequate drainage (IRC*R401.3, R401.7.3).

The solution included engineered exterior and interior piling. These costly foundation problems and this costly litigation could have been avoided by complying with said requirements. 

Save

Save

Masonry in the Media: Casa Azul, Chapultepec Castle, & More
June 2026

A film’s settings can take viewers to new locations, all from the comfort of their own home. It immerses them in the scenes, whether they take place in an opera house in Brazil or a grand mansion in Mexico City. Explore how these Latin American masonry ma

Chairman’s Message: When Things Don’t Go as Planned
June 2026

Not every day in this business goes the way we planned. Some days, everything lines up. The crew is moving well. Materials are on time. The job is flowing the way you hoped it would. And then there are the other days. The ones where something breaks. T

Marvelous Masonry: Borobudur
June 2026

For masonry contractors and suppliers, few structures offer as much practical insight as Borobudur. Built in the 9th century in Central Java, this massive stone monument remains as one of the most advanced examples of large-scale masonry construction ever

Wrapping Up Our Year And A Look Ahead
June 2026

It is amazing another year has gone by and what a year it has been. We have seen a lot of progress on so many fronts. All of this happens specifically due to the support of our members. Your support this past year is positioning our industry to make huge